Skip to content

Your first map ​

This tutorial takes you from an empty account to a working goal map. Everything here works the same in the cloud version and on your own server.

1. Create a project from a template (or blank) ​

After signing in you land on Projects. Click New project — the dialog has Blank and From template tabs. The fastest way to see what the app can do is a ready-made template: the gallery offers 40 of them (SWOT, PDCA, GROW, Business Model Canvas, 8D report, …), sorted by category.

Besides the name, the dialog has a Project color, for a template with deadlines a Start date (deadlines will be calculated) — the template is recomputed from the day you enter — and, if you keep clients in time tracking, a Client (optional) field. Where the AI assistant runs, there is also a link at the bottom: Or let AI draft the project…

New project — the From template tab. Once you pick a template with deadlines, a Start date appears that shifts them all.

You can look at a template first: a card in the gallery has an Open template button, the map opens as a preview with the banner Template preview — nothing is saved, and the project is only created with Use template.

Every template opens as a preview first — nothing is created until you confirm.

2. Find your way around the map ​

A map is a tree of goals. At the top sits the apex (main goal) — the circle with the overall progress ring. Below it are goal nodes: each has a status (To do / In progress / Done), and parents compute their progress from their children.

A small real map. Statuses color the nodes; the amber date badge is a deadline, a red one is overdue.

A few things worth knowing right away:

  • Add a sub-goal with the + Add subgoal button on any node — the new node finds a free spot without reshuffling the rest of the map.
  • The goal detail opens with a double-click on the node, or with the pencil on the card (next step). In a shared map where you are only a collaborator, the detail opens on your own steps; other people's steps you can look at.
  • The apex cannot be deleted — only renamed. The app says so itself: The main node cannot be deleted. Only the whole project can be deleted, from the home page.
  • Status changes by clicking the status label on the node — To do → In progress → Done.

The map's top bar has three menus with a fixed label and one button that combines them:

The map bar: Arrange (layout style), Sort (order of sub-goals), Readability (text size) and Bottlenecks.
Bar elementWhat it does
Arrange ▾Picks the layout style — wide, compact, around center — and rearranges the map right away. The menu can lock the style for every map. Details in Arranging.
Sort ▾Sorts the sub-goals under each parent by the chosen key (deadline, status, …). The map structure stays the same. See Sorting sub-goals.
Readability ▾Text size in nodes — normal, larger, title only. Nodes stay where they are. See Readability.
The frame buttonTidy the map by your settings (Arrange and Sort) and show all of it — when the layout gets messy, this puts it right with one click.
Portrait / LandscapeThe direction the tree grows.
BottlenecksHighlights the steps holding up the others. See Bottlenecks.

In the map's left rail you find the Tasks of this project icon (the task list of this map only) and the Rules bolt (the map's automations).

3. Open a goal's detail ​

Double-click any node (or click the pencil). The detail is split into categories in the dialog's left column:

CategoryWhat you set there
BasicsName, description, status, icon and colors of the node.
AssignmentDeadline, Assignee (the responsible person) and the Recurrence switch (daily / weekly / monthly).
AttachmentsFiles or links pinned to the goal (Add attachment, Add link).
Tasks & commentsSub-tasks and the discussion under the goal.
HistoryThe node's change history.
AutomationWho performs this — Person or Automation; the Wait for children switch; the rules of this node.
PositionOnly in the org-structure map — who holds the position and who covers for them.
The goal detail. Categories on the left; the deadline and assignee are in Assignment, “Who performs this” in Automation.

If you assign someone who has no access to the map, the app offers to share it right away. The assignee is always a human — even for a goal performed by an automation, the notifications go to the assignee.

4. Add tasks ​

A task is a goal with an assignee or a deadline — not a special kind of record. Break small, concrete work into sub-goals and give them an assignee or a deadline. The other way is the New task button on the Tasks page: pick the Project and the Parent goal (or Main goal (top)), type a title, and the app adds: set the assignee and deadline in the next step.

The Tasks page — the same list as a Table, a Timeline or a Kanban. The Calendar has its own page in the main navigation.

Worth knowing about the Tasks page:

  • Three views: Table · Timeline · Kanban. The Calendar has been a separate page in the main navigation since version 0.83 (deadlines, events, time off).
  • From a map you get here with the Tasks of this project icon in the left rail — a bar Project tasks: … with a Back to map link then shows at the top.
  • The list loads the first 500 tasks; larger organizations get a Load all button below the table.

5. Watch the progress ​

Every project card on the Projects page has a Dashboard button: overall completion, progress per pillar (a pillar is a first-level goal directly under the apex), who owns what, what is overdue and what changed recently.

The dashboard also saves to PDF (the Save PDF button) — handy for a weekly status mail.

Every project has a sequential number (Project number on the dashboard). Telling the assistant “open 12” is enough, and the Archive searches by it.

When it's done ​

When you finish the last goal, the map asks whether to move the project to the archive. Any other time you do it from the map menu ⋮ → Archive project. Archived projects live on the Projects page under the Archive (N) link — searchable by title or #number — and the Restore from archive button brings them back.

Limits and common snags

  • The apex cannot be deleted. It only goes away with the whole project, which is deleted from the home page.
  • “This map was changed in the meantime” — this dialog shows when someone else edited the map at the same time (or you did, in another window). It offers Load current version (discards your drafted edits), Keep my changes (overwrites the other person's) and Download backup (JSON). Nothing is discarded without your say. More in Collaboration and conflicts.
  • In a shared map as a collaborator you change status only on goals where you are the responsible person; on someone else's step you can propose a different due date — only the assigner changes it.
  • A goal with an assigned task (an assignee and a deadline) can be removed from the map only by the assigner or the project owner.

Next ​

Open source under the MIT license · © Tengo s.r.o.